Excavation Begins for 2-inch Distribution Line at Sitio Talinga
The Casiguran Water District (CWD) Production Team, led by Engr. Jomar H. Venus, with the strong support and bayanihan spirit of the residents, began excavation work at Sitio Talinga, Brgy. San Juan on Sunday, July 13, in preparation for the installation of a 2-inch distribution pipeline, aimed to enhance the water supply and improve water pressure in the area.
The 2-inch distribution line spans 1,260 linear meters and has an allocated budget of PHP 419,625.00, fully funded through the supplementary budget of the Casiguran Water District.
The excavation is currently ongoing and is expected to be completed within the week. The entire project is projected to be completed by the end of July.
The Casiguran Water District, under the management of GM Engr. Eduardo P. Tejada extends its gratitude to the officials of Brgy. San Juan, led by Hon. Capt. Roberto Doma Sr., and the residents of Sitio Talinga for their continued support and cooperation to ensure the smooth progress of the project.